Project 2000 dates not correct when I change project calendar

  • Thread starter Web project manager
  • Start date
W

Web project manager

I set up a calendar where I define 6 hours to the day and 30 hours for the
week. If I put in a project for 30 hours, it shows a duration of 5 days but
the start and finish dates are less than 5 days in duration. They are four
days which I believe is due to the dates being caculated based on 8 hour days.

Its got my whole project out of sync!
 
J

JulieS

Hi Web project manager,

You need to make changes in two places: Change the calendar through
Tools>Change Working Time and edit each working day (select M>F in the column
headings) to the 6 hours per day.

Then go to Tools>Options, calendar tab. Edit the hours per day to 6 and the
hours per week to 30. You will need to change the durations in any tasks you
have already entered, if you used days.

Hope this helps. Let us know how you get along.

Julie
 
M

Mike Glen

Hi Web project manager ,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 