I set up a calendar where I define 6 hours to the day and 30 hours for the
week. If I put in a project for 30 hours, it shows a duration of 5 days but
the start and finish dates are less than 5 days in duration. They are four
days which I believe is due to the dates being caculated based on 8 hour days.
Its got my whole project out of sync!