R
RM Martell
I am trying to create a basic schedule where I do not know the Duration of
tasks/events, but I know the start and end date, which will not change. In
the past I have been able to enter any two of the following and Project would
calculate the third: Start Date, End Date, or Duration, but for some reason
it is no longer doing it.
I am using the standard duration column, and this is a brand new file, so
there are no pre-existing constraints or links between tasks, resources or
even other tasks. I am entering the task name, then tabbing over the
Duration field and landing on the Start Date field, I enter the Start Date,
let's say 5/1/07 and then I tab to the End Date field, and enter 5/10/07.
When I move out of the End Date field, the Start Date changes to 5/10 and the
duration stays as 1 estimated day.
This just started occurring over the past few weeks, so I am sure there is a
setting I accidentally turned "on" or "off". Any suggestions?
tasks/events, but I know the start and end date, which will not change. In
the past I have been able to enter any two of the following and Project would
calculate the third: Start Date, End Date, or Duration, but for some reason
it is no longer doing it.
I am using the standard duration column, and this is a brand new file, so
there are no pre-existing constraints or links between tasks, resources or
even other tasks. I am entering the task name, then tabbing over the
Duration field and landing on the Start Date field, I enter the Start Date,
let's say 5/1/07 and then I tab to the End Date field, and enter 5/10/07.
When I move out of the End Date field, the Start Date changes to 5/10 and the
duration stays as 1 estimated day.
This just started occurring over the past few weeks, so I am sure there is a
setting I accidentally turned "on" or "off". Any suggestions?