Hi,

I have a project where the tasks belong to different resources.

By using filters, I am trying to get the resource usage view to show only
the resource totals for tasks against the filter I have applied. The filter
lists out the selected tasks okay, but the totals against the resource
contain all the tasks details (i.e work, %cmpl, etc) for the resource and
ignores the filter.

Does anyone know how I can show the resource totals for only those tasks I
have chosen?

Thanks

Paul
 