Project 2003 Resource Usage View

C

ccunning99

I am using Project 2003.

Is there any way to change the way the dispay shows the Resource Usage?
I would like to eliminate the weekend days from the view, as our team
does not work on the weekends. Does anyone know if this is possible.

Thanks
Chris
 
J

Jonathan Sofer

I am not aware of any way to do this. You can only change the color and
pattern of the non working days. What about showing the work in weeks
rather than days, this way you will not see the non working weekends in the
view. Sorry I couldn't be more help than that.

Jonathan
 
M

Mike Glen

Hi Chris,

Welcome to this Microsoft Project newsgroup :)

No, sorry: a calendar is a calendar! (And you might be forced to work
overtime some day to catch up).

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top