Reggie,
I have been asking if it is possible to run a query to return values for
resources where on certain days the resource has no work scheduled AND no
remaining availability - the latter being as a result of the days in
question having been "blocked out" in the individual resources calendar,
sadly I have been advised this is not possible using SQL & Project Server.
In the absence of the neat solution expected above the only way you can
attempt to gauge the overlap of resource holidays is to modify the Resource
Usage view as follows:
In the Resource Usage view add including 2 additional fields in the view,
Remaining Availability and
Overallocation. You can do this by right clicking on the timephased element
of the screen and selecting these fields from the list provided. In order to
make the information more meaningful/less confusing I tend to make the
Remaining Availability stand out by changing the cell colours from yellow to
another
colour - this results in a contrasting band of values running horizontally
across the timephase display. At the resource level you will see the 3
values and "at a glance" see if there are any points in time where the
resource has a Remaining Availability value. You can zoom out to view 3 days
or a week at a time which provides a quick short term perspective on demand
for resources.
You can "collapse" all the resources in this view by clicking once on the
Resource Name column heading and then clicking the - sign button on the
Formatting Toolbar, this will provide you with a high level view on demand
for each resource in your resource pool.
This approach will give you a high level view on the workload or non-working
time for your resources, I hope this is of some assistance.
--
Dominic Moss
www.projectability.co.uk
Helping people achieve more with Microsoft Project
Tel +44 8707 303 400
Fax +44 8707 303 500