John.Spradlin
I want to use project to manage an elections office. I want to set
the Finish Date (Election Day) and have project calculate backwards
the tasks to be done. By Law, certain tasks must be performed 10, 35,
75, etc.. days prior to election day. I want ot save a master
template for future elections, as most have the same rules. Then,
open the template, enter a new finish date for a new election and have
all the critical dates calculated backwards.
Is this doable with MS Project? Please reply to the gmai account.
Thanks