project change my selected date for the next day!!!!

J

Jéjé

Hi,

every time I select a date for a task (start date for example)
then project select the next day!!!!

I select 12 may 2005, project display and select the 13 may 2005!!!!

what'S appends?
there is any option anywhere?

the problem appear in all projects.

Thanks.

Jerome.
 
J

Jan De Messemaeker

Hi,

You are not supposed to enter dates, Project will calculate them for you
from dependencies and constraints.
When you enter a start date all Project registers is a Start No Earlier Tan
constraint.
If there is any other reason to postpone the task such as a dependency then
the tak will not show the start date you entered but a later date.
Hope this helps
 
J

Jéjé

We setup the project by using "elapse dates" instead-of "working hour"
(don't ask me why....) :)
we have try some parameters in the task, but the problem still here.

I have not tested from another computer for the moment.
 
J

Jan De Messemaeker

You can send me the file I shall have a look

jandemesATprom-ade.be

Greetings,
 