U
Uthall
Hi,
I really need help with this, it seems so simple in theory.
I have 2 tasks both with 24 hours work effort
Task 1 starts on day 1 and is spread at 50% alLocation of resource
across 6 days...i.e 4 hours per day for 6 days.
Task 2 starts on day 3, and i want it to use the remaininmg 4 unuse
hours per day, plus a full day on day 7.
It seems logocal and simple, but how do you do it?
Help......
I really need help with this, it seems so simple in theory.
I have 2 tasks both with 24 hours work effort
Task 1 starts on day 1 and is spread at 50% alLocation of resource
across 6 days...i.e 4 hours per day for 6 days.
Task 2 starts on day 3, and i want it to use the remaininmg 4 unuse
hours per day, plus a full day on day 7.
It seems logocal and simple, but how do you do it?
Help......