Project, make a variable duration task with SS and FF dependancie

A

Alan McArdle

Hi, in project I want a task with variable duration, start and finish
controlled by SS and FF dependancies from other tasks. How to do it?
The task is actually supervision of many other tasks in a project, and
continues from the 'start' to the 'finish' milestones.
 
J

John

Alan McArdle said:
Hi, in project I want a task with variable duration, start and finish
controlled by SS and FF dependancies from other tasks. How to do it?
The task is actually supervision of many other tasks in a project, and
continues from the 'start' to the 'finish' milestones.

Alan,
The type of task you are seeking is called a Hammock task. For
information on how to set it up, go to our MVP website at:
http://project.mvps.org/faqs.htm
and read FAQ 19 - Hammock tasks.

Hope this helps.
John
Project MVP
 
A

Alan McArdle

Exactly what I was looking for (why isn't this info in the help section?)
Thanks , Alan.
 
J

John

Alan McArdle said:
Exactly what I was looking for (why isn't this info in the help section?)
Thanks , Alan.

Alan,
There are a lot of "tricks" that can be used with any application.
Normally the application Help file will not attempt to explore all of
these "outlying" methods. That is one reason this newsgroup exists -
share the experience.

You're welcome.

John
 