Project specific calendar format change

M

mikejw

Hello,

Using MS Project 2003 Standard, can you change the format on a specific
project only (in my case, changing the calendar format using Tools, Options,
View to include the hours)? When I make the change to my project, it changes
every project to the same format regardless if the project is open or not.

Thanks again.

Mike
 
G

Gérard Ducouret

Hello Mike,

Sorry : no, you can't. The options in this View folio applie to all the
projects.

Gérard Ducouret
 
J

JulieS

Hi mikejw,

As you have discovered, changing the default date format through Tools >
Options changes the format for all project files. You can control on a
table by table basis what the date format is.
Choose Table > More Tables. Select the table that is part of the view and
click the Edit button. You can set specific dates formats in the Table
Definition dialog box.

Hope this helps. Let us know how you get along.

Julie
 
M

mikejw

Thanks for the responses.

JulieS said:
Hi mikejw,

As you have discovered, changing the default date format through Tools >
Options changes the format for all project files. You can control on a
table by table basis what the date format is.
Choose Table > More Tables. Select the table that is part of the view and
click the Edit button. You can set specific dates formats in the Table
Definition dialog box.

Hope this helps. Let us know how you get along.