T
tim
Here's the issue, a co-worker asked me to troubleshoot his
schedule. "Some" of the tasks in this respective project
schedule will not revert to the project start date when
changed to ASAP. Some remain at whatever the former
constraint date was, others change to a common date, but I
find no significance to that "common" date. And this all
happens without task predecessors or successors, which
might also have been removed or never were in place.
schedule. "Some" of the tasks in this respective project
schedule will not revert to the project start date when
changed to ASAP. Some remain at whatever the former
constraint date was, others change to a common date, but I
find no significance to that "common" date. And this all
happens without task predecessors or successors, which
might also have been removed or never were in place.