ConfusedFellow
Hello,
I guess I have made some mistakes when creating the project in Project 2003.
In the project, I have columns "Start","Finish","Actual Start" & "Actual
Finish" and etc. "Start" column lists the date when the task is supposed to
start and "Actual Start" column lists the date when the task actually starts.
The problem is that whenever I change the date under "Actual Start" column
to anything from NA, the date value under "Start" column changes as well.
In summary, "Start" date changes whenever "Actual Start" date changes.
Can anybody let me know what I did wrong and how I can solve this annoying
issue?
Thanks a million.
I guess I have made some mistakes when creating the project in Project 2003.
In the project, I have columns "Start","Finish","Actual Start" & "Actual
Finish" and etc. "Start" column lists the date when the task is supposed to
start and "Actual Start" column lists the date when the task actually starts.
The problem is that whenever I change the date under "Actual Start" column
to anything from NA, the date value under "Start" column changes as well.
In summary, "Start" date changes whenever "Actual Start" date changes.
Can anybody let me know what I did wrong and how I can solve this annoying
issue?
Thanks a million.