Project Summary Task

D

dee

Just wondering what the difference is between showing the Project Summary
Task as opposed to inserting a regular task that is the summary of all tasks.


Which is better? I am thinking perhaps Project Summary as it will appear in
reports and doesn't require any linking?

Thanks so much for any input!
 
G

Gérard Ducouret

Hello Dee,

There is no real difference between these two kind of summary task. The
Project Summary just saves a WBS level.

Gérard Ducouret
 
D

dee

Makes sense. Thanks for the clarification!
--
Thanks!

Dee


Gérard Ducouret said:
Hello Dee,

There is no real difference between these two kind of summary task. The
Project Summary just saves a WBS level.

Gérard Ducouret
 
D

dee

Hi Mike,

I think I worded my question incorrectly. Don't worry, I have learned 100%
that I shouldn't link summary tasks. I promise! :)

Thanks so much for all of your help.
 
M

Mike Glen

Good :)

Mike Glen
Project MVP


dee said:
Hi Mike,

I think I worded my question incorrectly. Don't worry, I have learned
100%
that I shouldn't link summary tasks. I promise! :)

Thanks so much for all of your help.
 