R
reallux
I have tasks that are not that important but still need to be in the project
timeline. These are tasks beyond the project end date further in the future.
I want to use the project count back feature in the project time scale (-5,
-4, -3 months from end date) from the project end date but is it using the
end date of the not important tasks.
Now it looks like we have 2 months of extra time which we do not have
Can I overcome this problem? Any help is appreciated.
Thanks
timeline. These are tasks beyond the project end date further in the future.
I want to use the project count back feature in the project time scale (-5,
-4, -3 months from end date) from the project end date but is it using the
end date of the not important tasks.
Now it looks like we have 2 months of extra time which we do not have
Can I overcome this problem? Any help is appreciated.
Thanks