C
Captain Paralytic
A riddle worthy of a Hobbit I'm sure.
But seriously, I think I've worked out how something works and I want
to test if my understanding is correct.
First of all a statement: "The default working time in Project is 08:00
to 17:00." That's it, you can't change it. That is always what Project
believes the absolute default working time to be.
If you go into Tools->Change Working Time... and alter the settings for
the "Standard (Project Calendar)" (e.g to 09:00 to 17:00) by drag or
shift marking M, T, W, Th, F, then this is now an edited, non-default
working time. The default working time is still 08:00 to 17:00.
If you now add a resource whose Working time is set to "Use default",
it will not use the Project default of 08:00 to 17:00 but will instead
inherit the working time from its base calendar (in this case the
Standard (Project calendar). All the week days on its calendar picture
will show as edited working hours.
So "Use default" working time for a resource means use the working
times in the associated base calendar. Whereas, "Use default" working
time in a base calendar means use Project's non-changeable default of
08:00 to 17:00.
Then of course we have Tools->Options...->Calendar where we have a
"Default start time" and "Default end time" and a "Set as Default"
button. These defaults have no connection whatsoever with either
Project's default working time of 08:00 to 17:00, on which the "Use
default" for a base calendar is based, or the "Use default" for a
resource calendar.
Well that's all clear then!
But have I got this correct?
But seriously, I think I've worked out how something works and I want
to test if my understanding is correct.
First of all a statement: "The default working time in Project is 08:00
to 17:00." That's it, you can't change it. That is always what Project
believes the absolute default working time to be.
If you go into Tools->Change Working Time... and alter the settings for
the "Standard (Project Calendar)" (e.g to 09:00 to 17:00) by drag or
shift marking M, T, W, Th, F, then this is now an edited, non-default
working time. The default working time is still 08:00 to 17:00.
If you now add a resource whose Working time is set to "Use default",
it will not use the Project default of 08:00 to 17:00 but will instead
inherit the working time from its base calendar (in this case the
Standard (Project calendar). All the week days on its calendar picture
will show as edited working hours.
So "Use default" working time for a resource means use the working
times in the associated base calendar. Whereas, "Use default" working
time in a base calendar means use Project's non-changeable default of
08:00 to 17:00.
Then of course we have Tools->Options...->Calendar where we have a
"Default start time" and "Default end time" and a "Set as Default"
button. These defaults have no connection whatsoever with either
Project's default working time of 08:00 to 17:00, on which the "Use
default" for a base calendar is based, or the "Use default" for a
resource calendar.
Well that's all clear then!
But have I got this correct?