D
Darlene
Dear Dale,
I tried the instructions you gave in a past post (see
below) regarding setting up Admin project, but I have some
questions...
I setup the projects the way you suggested and then
entered time against the tasks from my web access
timesheet. When I did this the % Work Complete changed to
100% complete. However, I want the task to have a fixed
duration of (say) 3 months and remain "open" so time can
be entered as required.
QUESTIONS:
1. Can we keep this task in my timesheet and keep
recording time against it even though it shows 100%.
2. Using this method will tasks always show 100%
complete. Is this OK?
3. Is there a better way to setup Admin type tasks that
multiple resources need to charge time against on an on-
going basis, and as the activity occurs?
I appreciate any help you can give in this regard.
Darlene
***********PAST POST***********
Andreas --
What you are describing is what many refer to as
an "administrative
project", which can be used to track non-project work
(such as support, team
meetings, etc.) and non-deliverable project work (such as
project meetings,
project management, project administration, etc.). You
are definitely on
the right track in creating one to accomplish your stated
purpose. In
addition, I believe you should consider doing the
following:
1. Set each of the tasks in your administrative project
to Fixed Duration
and non-Effort Driven
2. Assign your resources at 0% Units to each task.
The second step will cause each resource to be assigned to
0 hours of Work
on each task, but when you publish these tasks, each task
will appear on
each user's timesheets in PWA. Your team members can then
enter their
actual hours for each task whenever work is actually
performed.
I have personally used this technique and have recommended
it to my clients,
and it works. Hope this helps.
I tried the instructions you gave in a past post (see
below) regarding setting up Admin project, but I have some
questions...
I setup the projects the way you suggested and then
entered time against the tasks from my web access
timesheet. When I did this the % Work Complete changed to
100% complete. However, I want the task to have a fixed
duration of (say) 3 months and remain "open" so time can
be entered as required.
QUESTIONS:
1. Can we keep this task in my timesheet and keep
recording time against it even though it shows 100%.
2. Using this method will tasks always show 100%
complete. Is this OK?
3. Is there a better way to setup Admin type tasks that
multiple resources need to charge time against on an on-
going basis, and as the activity occurs?
I appreciate any help you can give in this regard.
Darlene
***********PAST POST***********
Andreas --
What you are describing is what many refer to as
an "administrative
project", which can be used to track non-project work
(such as support, team
meetings, etc.) and non-deliverable project work (such as
project meetings,
project management, project administration, etc.). You
are definitely on
the right track in creating one to accomplish your stated
purpose. In
addition, I believe you should consider doing the
following:
1. Set each of the tasks in your administrative project
to Fixed Duration
and non-Effort Driven
2. Assign your resources at 0% Units to each task.
The second step will cause each resource to be assigned to
0 hours of Work
on each task, but when you publish these tasks, each task
will appear on
each user's timesheets in PWA. Your team members can then
enter their
actual hours for each task whenever work is actually
performed.
I have personally used this technique and have recommended
it to my clients,
and it works. Hope this helps.