re-baseline

J

Jack

I've created my baseline plan and started adding actual work. If I realize
that my estimates are pretty inaccurate and I have additional tasks to add as
well, I would like to clear the original baseliine and save a new baseline.
If I do that, do I lose all the actual work hours that I've added?
 
J

Jan De Messemaeker

Hi,

Not at all!
All baselining does is copying the currently planned values into "safe
areas" called baselinestart, baselinefinish, baselineduration, baselinework
and baselinecost.
It does not touch planning or actual data.
 
J

Jack

Thank you very much, Jan.

Jan De Messemaeker said:
Hi,

Not at all!
All baselining does is copying the currently planned values into "safe
areas" called baselinestart, baselinefinish, baselineduration, baselinework
and baselinecost.
It does not touch planning or actual data.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm