P
pepper
OK, I'm starting to use Project again, haven't touched it
since '96 or before.
I am working on a project that is a launch of multiple
products.
In the past I used to be able to put a task in my project
that was called "launch date" and then I could schedule
all of my tasks to be due 1 week before to be
essentially "task X - 1W". Then, if there was a change
in the launch date I just moved that one task and
everything else fell into place.
I went throught the help file and have searched all over,
the problem is that I am not a project manager by trade
and I don't know how to find this functionality because I
don't know what to call it.
Thanks in advance.
since '96 or before.
I am working on a project that is a launch of multiple
products.
In the past I used to be able to put a task in my project
that was called "launch date" and then I could schedule
all of my tasks to be due 1 week before to be
essentially "task X - 1W". Then, if there was a change
in the launch date I just moved that one task and
everything else fell into place.
I went throught the help file and have searched all over,
the problem is that I am not a project manager by trade
and I don't know how to find this functionality because I
don't know what to call it.
Thanks in advance.