Reassigning plan owership

D

Doug Stephens

How to I reassign ownership of a plan from one PM to
another? I am currently loading plans from MS Project
2000 to 2003 Server EPM, but have defined myself as the
owner. I need to be able to reassign these plans to PMs.

Any ideas?
 
R

Rod Gill

You may get a more accurate answer in the Project Server group, but my
understanding is that you get the new project manager to re-publish the
project and all assignments. In the assignment publish there is a notify
resources with email option that can be turned off to avoid re-sending
emails.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.project-systems.co.nz/
Email rodg AT project-systems DOT co DOT nz
 