M
Mary Ann
What is the difference between keeping the default setting for recurring task
calendar and setting it to None?
The Microsoft Help gives the following:
By default, tasks are scheduled based on the working time of the project
calendar and of resources assigned by their working times. If the option is
set to None, then the task is scheduled based on the project calendar and on
the calendars of any assigned resources.
They seem to be the same to me. Can anyone add any light to this - want to
understand!
I am using Project 2003
calendar and setting it to None?
The Microsoft Help gives the following:
By default, tasks are scheduled based on the working time of the project
calendar and of resources assigned by their working times. If the option is
set to None, then the task is scheduled based on the project calendar and on
the calendars of any assigned resources.
They seem to be the same to me. Can anyone add any light to this - want to
understand!
I am using Project 2003