A
Amit
Hi All,
Please help me in understanding the calculation done by Project when a
new resource is assigned to a task. Following is the scenario...
i create a new task (Fixed unit - effort driven) with duration 9 days
and assign two resources r1 and r2 with units 115% and 85%. Project
calculates the duration as 9 days with individual effort as 82.8 and
61.2 hrs respectively. This comes as expected.
Now, if i change the unit for the resource r1 from 115% to 100%, the
individual efforts (and total effort) remain fixed but the duration of
the task changes to 10.35 days with r1 becoming the driving resource.
Now, if i add a third resource r3 to the task with units 90%, the
duration of the task changes to 6.82 days and individual efforts change
to 54.57, 40.33 and 49.1 hrs respectively for r1, r2 and r3.
These individual efforts donot satify the formula
(Individual Assignment)/(Total Assignment) * Total Effort
This is because of the intermediate step of reducing the units which
caused change only in duration and not the individual effort.
How is the Project calculating these individual efforts and the new
duration in the last step?
Thanks,
Amit
Please help me in understanding the calculation done by Project when a
new resource is assigned to a task. Following is the scenario...
i create a new task (Fixed unit - effort driven) with duration 9 days
and assign two resources r1 and r2 with units 115% and 85%. Project
calculates the duration as 9 days with individual effort as 82.8 and
61.2 hrs respectively. This comes as expected.
Now, if i change the unit for the resource r1 from 115% to 100%, the
individual efforts (and total effort) remain fixed but the duration of
the task changes to 10.35 days with r1 becoming the driving resource.
Now, if i add a third resource r3 to the task with units 90%, the
duration of the task changes to 6.82 days and individual efforts change
to 54.57, 40.33 and 49.1 hrs respectively for r1, r2 and r3.
These individual efforts donot satify the formula
(Individual Assignment)/(Total Assignment) * Total Effort
This is because of the intermediate step of reducing the units which
caused change only in duration and not the individual effort.
How is the Project calculating these individual efforts and the new
duration in the last step?
Thanks,
Amit