S
Swansea Jack
Hi All 
I know I'm doing something wrong but I can't spot it - it's driving me nuts!!!
I have tasks that are in progress with actual start dates & % completes
filled in. However, where these are behind schedule (ie behind the new status
date) the remaining duration is calculated from the progress point (ie the
complete through date) not the status date. Basically I want it to show a
task with three weeks remaining from the status date, not 6 weeks from the
progress point which is 4 weeks behind the status date so only shows a bar
two weeks beyond the status date.
I guess this is something to do with a switch on the tools/options menu but
I've tried all the combinations and none seem to make any difference.
Please can you help !!!!
I know I'm doing something wrong but I can't spot it - it's driving me nuts!!!
I have tasks that are in progress with actual start dates & % completes
filled in. However, where these are behind schedule (ie behind the new status
date) the remaining duration is calculated from the progress point (ie the
complete through date) not the status date. Basically I want it to show a
task with three weeks remaining from the status date, not 6 weeks from the
progress point which is 4 weeks behind the status date so only shows a bar
two weeks beyond the status date.
I guess this is something to do with a switch on the tools/options menu but
I've tried all the combinations and none seem to make any difference.
Please can you help !!!!