Hi Steve,
You are worried that when you modify a calendar you MAY enter a
wrong
working time since you have to make an assumption.
Well, putting a resource on say 50% assumes he/she will work 30
seconds
every minute, and that is CERTAINLY not reality.
Changing a calendar may be right, percentage are always wrong..
Greetings,
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"Steve House [Project MVP]"
<
[email protected]>
schreef in bericht I agree with you there. Rather than have a task stretch out over
a week
with Joe working on it 25%, I'd rather put him on it 100% So I can
'git
'er
done' in one day and move on with the rest of the project. But I
do
think
that the resource calendar should reflect the total time the
resource is
physically "on the property" as they used to say in North American
railroads
and not have any times backed out for time he's there but not
available
to
the project. The problem I have with adjusting the resource
calendar is
you
have to make assumptions about WHICH hours out of the workday he's
going
to
work on your project tasks and which hours are going to be
reserved as
project non-working time. Joe is allowed to you 50%. That's 4
hours per
day so if you use the idea of modifying his work calendar, you
must
arbitrariily decide to set his calendar showing hours of work of,
say,
only
from 8am to noon, even though he is physically present from 8 to
5. You
assign Joe to a task "B" that has a predecsessor task "A." The
predecessor
happens to end Monday at noon. The schedule will place B starting
Tuesday
at 8am because you've told it Joe is nowhere to be seen after noon
on
Monday. In fact, you could have asked Joe to take care of his
other,
non-project, obligations Monday moning instead of deferring them
to the
afternoon as he usually does, and then to work on the project task
in the
afternoon, thus getting task B done on Monday instead of delaying
it to
Tuesday. But if his resource calendar says he only works 8-12,
MSP won't
recognize that that's a valid option and there's no way to get it
to
schedule B on Monday afternoon without resorting to a task
calendar or
laboriously editing Joe's resource calendar day-by-day.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in
message
Hi,
As Julie said, there are schools of thought on this one.
I try to avoid percentages ANYWHERE in Project so I recommend to
enter
different working times.
Reasons are that working time is taken into account immediately
even if
you
modify it after the assignment, and that Resource leveling works
far
better.
HTH
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"tommcbrny" <
[email protected]> schreef in
bericht
OK, thank you. I like the idea of putting the full name in the
initials
field and using that on the task sheet as a work-around.
Is my method of limiting the hours a resource can be assigned
to the
project
flawed? Am I better off just reducing the number of hours
available
for
each
resource and leaving the max units at 100%?
I like the way I've done it better, but wonder what others
think and
how
others handle similar situations.
Thanks Julie and thanks Jan.
Tom
:
Hi Tom,
As noted by Jan in his post, the [%] you are seeing next to
the
resource's
name in the Resource Name column displayed in the Task sheet
is the
*assignment units* for that resource to that specific task.
By
default,
the
Resource Name column includes assignment units. If you just
assign
the
resource to the task, Project will assign the resource at
his/her
Maximum
units.
You can copy and paste the resource's name from the Resource
Name
column
in
the Resource Sheet to the Initials column. Then in the Task
Sheet
insert
the Resource Initials column and delete the Resource Name
column
from
the
view. The Resource Initials column will just show what ever
is
entered
into
the field without the [assignment units] appearing.
I hope this helps. Let us know how you get along.
Julie
message
Hello,
My mistake, I should have said the Task sheet, not the
Resource
sheet.
In regard to the percentage value showing up next to the
resource
name,
what
shows up is the Max Unit value that I specify for the
resource on
the
Resource sheet.
For instance, Resource 1 works an 8 hour day per my default
calendar,
but
only 25% of his time is dedicated to the project for which
I'm
producing
this
project plan. I set his Max Units to 25% on the Resource
sheet
(or
in
the
"Resource Availability" section of Resource Information ->
General
tab.
This way, a task requiring 1 day of work effort (8 hours)
will
take
4
days
for this resource to complete, as he is only dedicating 25%
of his
day
to
this project.
So, as soon as I set the Max Units to XX %, this percentage
begins
appearing
next to the resource name in the Resource Name column on
the Task
Sheet.
My question is really how to get rid of that percentage
value next
to
the
Resource Name in the Resource Name column of the task
sheet.
Thank you,
Tom
:
Hi,
The %available is not always displayed in the Gantt Chart,
what
you
see
is
teh % assigned; you may well have a resource 50% available
but
assigned
only
10% to a task.
By all means, if you want to see which resource and not
how much,
Through
the bar styles replace the right text (Resource Names) by
Resource
Initials
and make sure the initials field is meaningful.
The %available does NOT appear in brackets on the resource
sheet.
If
you
want to hide it, hide (=delete) that column.
HTH
--
Jan De Messemaeker, Microsoft Project Most Valuable
Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"tommcbrny" <
[email protected]> schreef
in
bericht
Hello,
I'm setting a % for max units available to reflect the %
of
time
my
resources work on a project.
When I do this, the unit % automatically appears in
brackets
after
the
resource name in the Gantt chart (resource name column
and
chart
bar)
and
on
the Resource sheet.
I do not want this percentage to be displayed. Is there
a way
to
change
formatting of the resource names to remove this
percentage
indicator?
Thanks,
Tom