When I go to assign a resource to a task in project, the 'remove' and
'replace' buttons are grayed out (ghosted). I was wondering how to get them
enabled again? We are not using a project server. We are using Project 2003
Professional with SP1.
'replace' buttons are grayed out (ghosted). I was wondering how to get them
enabled again? We are not using a project server. We are using Project 2003