George Wilson
I am assisting a customer using Project 2002 on a Windows
2000 system. A vacation day was scheduled for a resource
and the task and dependant tasks were updated to reflect
the extra day needed to complete the task. The vacation
day was designated by using the change working time
feature for that particular resource. The vacation day was
canceled and this tasks duration, start and end date are
correctly reflected, but the dependant tasks are still
showing the extra day for duration, start and end dates. I
would tend to think this should update automatically as it
did when the vacation was originally scheduled but it has
not. Is there an action that needs to be performed to
update the dependant tasks after this type of resource
reschduling?
TIA
George
2000 system. A vacation day was scheduled for a resource
and the task and dependant tasks were updated to reflect
the extra day needed to complete the task. The vacation
day was designated by using the change working time
feature for that particular resource. The vacation day was
canceled and this tasks duration, start and end date are
correctly reflected, but the dependant tasks are still
showing the extra day for duration, start and end dates. I
would tend to think this should update automatically as it
did when the vacation was originally scheduled but it has
not. Is there an action that needs to be performed to
update the dependant tasks after this type of resource
reschduling?
TIA
George