dave said:
Thanks -
I guess I need to clarify what I am trying to do:
Within the calendar view, is there a way to display only the task
name, only on it's finish date? (No duration, no bar, etc) I would
like to display project tasks similar to the outlook add-in where you
set start date = finish date for the view.
Dave,
To be honest, I don't know. I never use the Calendar view but playing
with it a little it might be possible to do what you want but it
certainly won't be pretty (i.e. very readable). What I ended up doing is
to set up a separate 1 day task on the Finish date of each task. Then I
filtered the view so only the one day tasks were visible. Finally I set
the Format/Bar Styles for a line bar type (noncritical task). Like I
said, not very "pretty".
Project isn't all that flexible when it comes to presenting the data in
certain ways and the Calendar view is one of them.
John
Project MVP