A
assaf1978
Hi Jim,
Consider a situation where you have versions of a software. Each version is
a project in a master gantt.
Once the version is released, I don't need it anymore so I can delete it.
But if i'll do that, I return all the other version's dates backwards
(they're connected to the deleted version) to their "start no earlier than"
date that was there when the gantt was created. I need the dates to remain as
they are now despite the deletion.
Thanks,
Assaf
Consider a situation where you have versions of a software. Each version is
a project in a master gantt.
Once the version is released, I don't need it anymore so I can delete it.
But if i'll do that, I return all the other version's dates backwards
(they're connected to the deleted version) to their "start no earlier than"
date that was there when the gantt was created. I need the dates to remain as
they are now despite the deletion.
Thanks,
Assaf