A
Alfatcop
Hello,
Here is the example. Let's say you have a task estimated to take 80 hrs with
a resource at 70% load (duration is then 14.3 days)
After 13 days, the resource is reporting 90 hours of work and the task is
not yet completed (and an estimated 10 extra hours will be needed)...
When reporting these 90 hours, MSPRO is automatically setting the task to
completed, ho w do I prevent this behavior?
Thanks
Here is the example. Let's say you have a task estimated to take 80 hrs with
a resource at 70% load (duration is then 14.3 days)
After 13 days, the resource is reporting 90 hours of work and the task is
not yet completed (and an estimated 10 extra hours will be needed)...
When reporting these 90 hours, MSPRO is automatically setting the task to
completed, ho w do I prevent this behavior?
Thanks