Reporting task

S

Steven

I previously had a vb / macro that created the following for me.
I want to be able to run a macro which asks for start and finish date and
creates a report which has the first resource on the project, highlights the
tasks they are involved in over the timeline I set and either saves this in a
separate plan or saves in html format so that I can email to the resource
 
J

Jim Aksel

Filter the Resource Usage View to show only the one resource.
In Project2003 use Save As HTML. Mail the HTML to the resource.
You can create a custom filter to specify the date range and even the
resource if desired.

Alternative would be to print the filtered view as a PDF file.
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 