S
Spunky
MS Project 2003 (11.2.2005.1801.15) SP2
Project Server 2003 SP1 (we have SP2 but were advised by our consultants to
not install)
What is a good way to have a to do list under a task so the task will
represent the duration of all and be resource loaded but yet have a list
below it of things to happen during that task being accomplished? I want
these visible on a line in the project not in the notes field. We are now
adding a task under a summary task to be the "summary" of the list below it.
We don't want it a summary task that rolls up because we want to resource
load, have dependancies and duration. The ones below are not resource loaded
but can show duraion. For visibility we are adding three dots on the
supporting tasks to indent them. Are we setting ourselves up for
complications later?
Project Server 2003 SP1 (we have SP2 but were advised by our consultants to
not install)
What is a good way to have a to do list under a task so the task will
represent the duration of all and be resource loaded but yet have a list
below it of things to happen during that task being accomplished? I want
these visible on a line in the project not in the notes field. We are now
adding a task under a summary task to be the "summary" of the list below it.
We don't want it a summary task that rolls up because we want to resource
load, have dependancies and duration. The ones below are not resource loaded
but can show duraion. For visibility we are adding three dots on the
supporting tasks to indent them. Are we setting ourselves up for
complications later?