M
Mike N.
I'm having the following problem with 2000:
Suppose a task is assigned to three people A, B, and C and their allocations
are 10%, 20%, and 30% respectively. The calendar time for the task is 4
weeks. So A charges 0.4 weeks, B charges 0.8 weeks and C charges 1.2 weeks. I
verify these times by going to the Resource Usage page. So far so good. Next,
suppose I want to increase the amount of work done on that task by B to from
20 to 40%. I would do this by clicking on the "Assign Resources" button, and
changing B to 40%. I would then look at the task duration on the Gantt chart
- it may or may not change (not sure why it changes only sometimes). If it
did change (e.g., to 2 weeks), I would change it back to 4 weeks by simply
clicking on it and changing it back. Now if I look at the Resource Usage
page, the hours charged by B have not changed to 1.6 weeks. They remain at
0.8 weeks. I can force a correction by entering 0 hours for a duration and
then re-entering 4 weeks.
Am I doing something obviously wrong? All of the task constraints are "as
soon as possible" and the task types are "fixed units" and "effort driven" is
checked. I would greatly appreciate any suggestions.
Thanx,
Mike
Suppose a task is assigned to three people A, B, and C and their allocations
are 10%, 20%, and 30% respectively. The calendar time for the task is 4
weeks. So A charges 0.4 weeks, B charges 0.8 weeks and C charges 1.2 weeks. I
verify these times by going to the Resource Usage page. So far so good. Next,
suppose I want to increase the amount of work done on that task by B to from
20 to 40%. I would do this by clicking on the "Assign Resources" button, and
changing B to 40%. I would then look at the task duration on the Gantt chart
- it may or may not change (not sure why it changes only sometimes). If it
did change (e.g., to 2 weeks), I would change it back to 4 weeks by simply
clicking on it and changing it back. Now if I look at the Resource Usage
page, the hours charged by B have not changed to 1.6 weeks. They remain at
0.8 weeks. I can force a correction by entering 0 hours for a duration and
then re-entering 4 weeks.
Am I doing something obviously wrong? All of the task constraints are "as
soon as possible" and the task types are "fixed units" and "effort driven" is
checked. I would greatly appreciate any suggestions.
Thanx,
Mike