S
Sergio
I have a question about Project that I have been unable to find an
answer to (at least in my usenet search):
I want to be able to implement my resoure allocation in a project such
that if the project lasts for example 2 months, I can have resource X
working 70% of his time on that project for the first month and 45% of
his time on that project for the second month.
Thus far, I can only figure out (a) how to allocate a fixed percentage
of someone's time for the duration of the task or (b), have to specify
explicit hours through the resource usage view. For example, I'd
ideally like to create a task that goes from September 1st to October
31st and then say "from September 1st to September 30th, X is allocated
70% to this project. From October 1st to October 31st, X is allocated
45% to this project".
Forgive me if the answer was already out there and I couldn't find it,
but any help would be much appreciated.
Thanks!
Sergio.
answer to (at least in my usenet search):
I want to be able to implement my resoure allocation in a project such
that if the project lasts for example 2 months, I can have resource X
working 70% of his time on that project for the first month and 45% of
his time on that project for the second month.
Thus far, I can only figure out (a) how to allocate a fixed percentage
of someone's time for the duration of the task or (b), have to specify
explicit hours through the resource usage view. For example, I'd
ideally like to create a task that goes from September 1st to October
31st and then say "from September 1st to September 30th, X is allocated
70% to this project. From October 1st to October 31st, X is allocated
45% to this project".
Forgive me if the answer was already out there and I couldn't find it,
but any help would be much appreciated.
Thanks!
Sergio.