Resource Allocation

D

Dniko

I have a client that would like to upload task and resources into another
system they have for resource planning. The issue is not the upload, but in
the resource planning on project. Here an example of what they are looing
for, and I can't figure out how to allocate properly, or if it's beyond the
capabilites of project.

They have 9 functional resources groups. Each of the nime functional
resouces are general designations for multiple resouces in each group. Here's
an example of what they are looking for.

Task: Structure Database; dur=5 days. (5 days is the time constraint, but it
will take 5 resources to complete) But since they want to show only one of
the general functional resources, how do I allocate 200 hours, in a 40 hour
week under one resource?
 
R

Rod Gill

You will need to have generic resources such as Business Analyst and assign
in this case at 500%
 