Hi,
I've been using MS Project for only a little while, and used to do all
levelling manually. Since my current project involves too many resources,
I'd like to find better ways. I have a few questions...
1) Can MS Project assign resources from a group of resources?
For example, I have 3 PLSQL programmers and 8 Java programmers. The PLSQL
tasks can be completed by either one of the PLSQL developers. Is there a way
to tell MS Project to select the best resource to optimize the result?
2) Our company uses multiple project plans, all linked to a master plan and
a single master resource file. If I decide to use automatic levelling of my
plan, will it affect the dates on the other plans? If yes, is there a way to
prevent it? I don't believe the owners of the other plans would like it very
much. --> Most of the resources on my plan are mine alone, but a few are
shared.
I've been using MS Project for only a little while, and used to do all
levelling manually. Since my current project involves too many resources,
I'd like to find better ways. I have a few questions...
1) Can MS Project assign resources from a group of resources?
For example, I have 3 PLSQL programmers and 8 Java programmers. The PLSQL
tasks can be completed by either one of the PLSQL developers. Is there a way
to tell MS Project to select the best resource to optimize the result?
2) Our company uses multiple project plans, all linked to a master plan and
a single master resource file. If I decide to use automatic levelling of my
plan, will it affect the dates on the other plans? If yes, is there a way to
prevent it? I don't believe the owners of the other plans would like it very
much. --> Most of the resources on my plan are mine alone, but a few are
shared.