Resource Assignment

B

Braker

I'm new to Project. I recently setup the Project Enterprise for a
manufacturing company I work for. The resources we need to track are
machines that require operators. I would like the operator to login web
access and log time on machine resources that have assigned tasks. For
instance if I have 5 machines and two operators then I need those two
operator to log hours for each individual machine with assignments. I
created user accounts in web access and then I added 5 machine resources in
enterprise global. I need to have operators login so I can tell if they
didn't put time in for a day they worked. If someone can point me in the
right direction I will be eternally grateful. Thanks in advance!
 
M

Mike Glen

Hi Braker,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
M

Mike Glen

You're welcome, Braker, it's always best to ask where the experts hang out
:)

Mike Glen
MS Project MVP
 