D
Diane76
I am fairly new to project management and have no guidance within my company,
so please forgive me if this question should be a straightforward one: I
have a set of tasks that can be done in any order by any one of 4 resources.
I have estimates for each task, but of course those can change. Basically,
we were hoping to assign resources from the group of 4 as we go, so whoever
finishes their task first, gets the next one in line. I would like to be
able to plug in the resource as I know who it is going to be, but still have
Project figure out my projected project completion date based on best-case
scenario, regardless of the resource. Is there a way to do this? Thank you
for any help you can provide.
so please forgive me if this question should be a straightforward one: I
have a set of tasks that can be done in any order by any one of 4 resources.
I have estimates for each task, but of course those can change. Basically,
we were hoping to assign resources from the group of 4 as we go, so whoever
finishes their task first, gets the next one in line. I would like to be
able to plug in the resource as I know who it is going to be, but still have
Project figure out my projected project completion date based on best-case
scenario, regardless of the resource. Is there a way to do this? Thank you
for any help you can provide.