Resource Cost for certain Time Period

J

jdescant

I am a semi-new user to Project. Have been using Primavera to
schedule a program previously. This is my 4th day with this new
employer and they want things yesterday!

I have a resource pool that is linked to 5 seperate projects and need
to capture planned resource cost for individual from April 1 to Sept.
30.

any help appreciated ....

J
 
J

Jan De Messemaeker

Hi,

In the resource usage view, set the minor timescale to months
Right-click on the right, Select Detail Styles then Cumulative cost, show
What you look for is the difference between cum cost through Sept minus cum
cost through March

HTH
 
J

J

Thanks .. that gives me the info I need and I can put something
together manually. I guess I was more looking for a way to dump all
that info into excel to be able to manipulate/show the data the way I
wanted to.
 
J

Jan De Messemaeker

Hi,

Why not ask that in the first place?
On the analysis toolbar, click Export Timescaled data to Excel.
HTH
 