Resource Graph Baseline View?

S

Steve Scott

Connected to my previous question...can I show a baseline work line on the
Resource Graph as well as work?
 
C

Catfish Hunter

I have had no success eith that but, Go to View>Resource Useage. Right mouse
ckick in the graphic are and choose Detail Styles. You can add baseline to
the data and any combinations of other data.
Good Luck
 