Resource Graph for Resource Group

V

VSAT Ryan

We all know that MS Project has a Resource graph for each individual resource
to show over/under allocations, but can MS Project do a similar graph, only
for resource GROUPS, rather than each individual resource?
 
J

Jan De Messemaeker

Hi,

Yes. See FAQ 38: Combined resource graphs
FAQs URL in my signature below.
HTH
 
R

Ratheesh

VSAT Ryan,

If you are using Project 2003 you can use "Assign Resources" (Short Key is
Atl + F10) feature, select a group of resources you want and then hit "
Graphs" button and in the opening screen select "remaining availability".I
guess this is the closest you can get.Perhaps there are other options note
sure please wait for otheres responces as well.

Hope this helps.
 