Hi

Is it possible to draw a Resource Graph (Resource Histogram) which would
show Resource allocation against Tasks and where more Resource maybe need on
certain days? The graph would have the Tasks on the X axis and the Days on
the Y axis.

Thank you.
 
J

John

Julia said:
Hi

Is it possible to draw a Resource Graph (Resource Histogram) which would
show Resource allocation against Tasks and where more Resource maybe need on
certain days? The graph would have the Tasks on the X axis and the Days on
the Y axis.

Thank you.

Julia,
Well yes, but not directly in Project. Project's Resource Graph will not
show task data versus time, only resource data versus time. The type of
graph you want could be created by exporting the data to Excel and
graphing there. There are a couple ways to do that, either develop a
custom VBA macro or use the "Analyze Timescaled data in Excel"
utility/add-in and then manipulate the data in Excel to produce the
graph you want.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top