D
David M C
Wouldn't it be good to be able to group resources into teams in the same way
tasks a grouped by Summary/Subtask. That way, you could assign a group such
as Electricians to a task, and Project could assign the appropriate resource
(perhaps using a similar concept to task priority).
This way, rather than realising a single resource is overallocated, you
could see the need for more of a particular type of work resource. It would
also allow you to see the total cost of a type of resource etc. Even if
Project couldn't level the resources based on its group, the extra summary
information would be useful.
It would also be useful to show summary task information in resource filters
and views, since you may have the same task name under many different summary
tasks. For example, PlaneA may have an Airframe task, but PlaneB may also
have an Airframe task. In the resource usage view, you can't see which
Airframe task applies to which Plane summary task.
Dave
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...bdbc-4d378a3cf0cb&dg=microsoft.public.project
tasks a grouped by Summary/Subtask. That way, you could assign a group such
as Electricians to a task, and Project could assign the appropriate resource
(perhaps using a similar concept to task priority).
This way, rather than realising a single resource is overallocated, you
could see the need for more of a particular type of work resource. It would
also allow you to see the total cost of a type of resource etc. Even if
Project couldn't level the resources based on its group, the extra summary
information would be useful.
It would also be useful to show summary task information in resource filters
and views, since you may have the same task name under many different summary
tasks. For example, PlaneA may have an Airframe task, but PlaneB may also
have an Airframe task. In the resource usage view, you can't see which
Airframe task applies to which Plane summary task.
Dave
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...bdbc-4d378a3cf0cb&dg=microsoft.public.project