I have a resource which has 2 tasks that has an overlapping work period. The
period of time when the 2 tasks overlap would be a 200% unit for the
resource.
Is it possible for me to assign a specific kind of task to only require 10%
of the resource's time and have MS Project deal with leveling the other task
to 90% (for the period of overlap)?
Effectively, I would see the completion time of both tasks to be later than
expected, since it has to be done by the same person and the start time is
fixed.
period of time when the 2 tasks overlap would be a 200% unit for the
resource.
Is it possible for me to assign a specific kind of task to only require 10%
of the resource's time and have MS Project deal with leveling the other task
to 90% (for the period of overlap)?
Effectively, I would see the completion time of both tasks to be later than
expected, since it has to be done by the same person and the start time is
fixed.