R
Robert
I am working on leveling some resources for a large project. Here is my
process. The first pass throught the WBS I linked tasks based on task
dependency. Then I went through then I filtered the WBS by each resource and
linked all their task Start to Finish. (The intent was to avoid
overallocation for the individual resource) I was successfull in my attempt
to not overallocate, but now I am in the opposite direction. Now the problem
is, when I look at the resource usage graphs for these resources, some weeks
they are dramatically underallocated. Is there an easier way then going task
by task, day by day, and adjusting the hours for each resource?
process. The first pass throught the WBS I linked tasks based on task
dependency. Then I went through then I filtered the WBS by each resource and
linked all their task Start to Finish. (The intent was to avoid
overallocation for the individual resource) I was successfull in my attempt
to not overallocate, but now I am in the opposite direction. Now the problem
is, when I look at the resource usage graphs for these resources, some weeks
they are dramatically underallocated. Is there an easier way then going task
by task, day by day, and adjusting the hours for each resource?