M
mek
How is resource overallocation calculated? What is the maximum percentage
amount of tasks that a resource can be assigned to (out of all the tasks for
the entire project) for MS Project to consider that resource to be
overallocated?
The problem that is happening is that I have one resource that has many
tasks assigned (without overlapping durations) and it seems like just because
the resource is scheduled a number of tasks MS Project is considering the
resource to be overallocated.
Any explanation would help.....thanks!!
amount of tasks that a resource can be assigned to (out of all the tasks for
the entire project) for MS Project to consider that resource to be
overallocated?
The problem that is happening is that I have one resource that has many
tasks assigned (without overlapping durations) and it seems like just because
the resource is scheduled a number of tasks MS Project is considering the
resource to be overallocated.
Any explanation would help.....thanks!!