Tom Bodolovich
I've got a curious problem that is probably easily
solved. I'm pretty new to project so excuse me if this is
overly simple.
I have set up a project with about 8 resources. When I
originally set up the project I set resource "A" to do
multiple tasks and it naturally kicked out the tasks based
on that resources availability. But since I have updated
the project, unstarted and unfinished tasks are assigned
to that resource to happen concurrently. I don't want to
add dependencies to the tasks as they are not dependent on
each other to finish. Why is project scheduling my
resource to work on 15 tasks with 4 hour durations each on
the same day??
solved. I'm pretty new to project so excuse me if this is
overly simple.
I have set up a project with about 8 resources. When I
originally set up the project I set resource "A" to do
multiple tasks and it naturally kicked out the tasks based
on that resources availability. But since I have updated
the project, unstarted and unfinished tasks are assigned
to that resource to happen concurrently. I don't want to
add dependencies to the tasks as they are not dependent on
each other to finish. Why is project scheduling my
resource to work on 15 tasks with 4 hour durations each on
the same day??