resource start date problems

R

RobR

I'm using Project 2003. So, I have a project plan
that was created at the start of a project months ago.
I've been asked to adjust the dates on the plan to
account for reality. I'm having a couple of issues
dealing with the best way to do this.

First I have Task B which is has a predecessor
of A. A ended 2 weeks late. If I adjust the
Finish date of A to reflect reality, B's start date
doesn't change.

Next question I have is I have two resources
assigned to Task C. I set task C to start
ASAP (when it's predecessor is complete).
Problem I'm having here is that Task C won't
start until BOTH resources I've assigned
to it become available (testers). I'd like
it to start as soon as the first resource
becomes available and the second one can
jump in when he's done with the conflicting
task. I'm not sure how to set this. Thanks!!!
 
J

Jan De Messemaeker

Hi Rob,

IS B a predecessor of A or does it HAVE A as a predecessor?

Next question: that is how Project works. No setting, it works the way you
want it to.
 
G

Gérard Ducouret

Hello Rob,

RobR said:
I'm using Project 2003. So, I have a project plan
that was created at the start of a project months ago.
I've been asked to adjust the dates on the plan to
account for reality. I'm having a couple of issues
dealing with the best way to do this.

First I have Task B which is has a predecessor
of A. A ended 2 weeks late. If I adjust the
Finish date of A to reflect reality, B's start date
doesn't change.

Did you create a finish to Start (FS) link from A to B ?
If yes, and B still doesn't move, check that B has not any Real Start nor %
Complete. Erase these 2 values.
Next question I have is I have two resources
assigned to Task C. I set task C to start
ASAP (when it's predecessor is complete).
Problem I'm having here is that Task C won't
start until BOTH resources I've assigned
to it become available (testers). I'd like
it to start as soon as the first resource
becomes available and the second one can
jump in when he's done with the conflicting
task. I'm not sure how to set this. Thanks!!!

Run a resource leveling : Tools / Level Resources... / Leveling can adjust
individual assignments on a task / Level now

Hope this helps,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top