P
Paul Ibison
Firstly I must mention that I'm pretty new to Microsoft Project so my
questions might show a completely wrong thinking! I have a parent summary and
a lot of child tasks which can be done at any time before a deadline. I've
set this up ok. I've assigned a resource at 20% (1 day a week) for the task
whose duration is 4 days. What I want is the task to now last 4 calendar
weeks on the Gantt chart - is this possible?
TIA,
Paul Ibison
questions might show a completely wrong thinking! I have a parent summary and
a lot of child tasks which can be done at any time before a deadline. I've
set this up ok. I've assigned a resource at 20% (1 day a week) for the task
whose duration is 4 days. What I want is the task to now last 4 calendar
weeks on the Gantt chart - is this possible?
TIA,
Paul Ibison