Resource Usage View

I

Ignacio

After I filled task name, resources, time, rate and finished all about this
step,
I swish from the Gantt chart view to Resource Usage view, some of the resource
I used in other projects and in the actual one are showed in this one to,
this Cause alteration in my entire new project. I would like to know what I
should do in this case.
Thank, I apprises any help, Ignacio
 
M

Mike Glen

Hi Ignacio,

Welcome to this Microsoft Project newsgroup :)

Tools/Resource Sharing/Sharing Resources.../check Using own resources.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
I

Ignacio

Hi, Mike. Thank for your help, I did what you tell me to do
And I see the option but do not allow me to do anything is not on.
I am trying to get that option through a different ways. We’ll if
I can do it. Thank one more time. Ignacio
 