K
Katherine
I have a number of projects that share resources.
I set up my resources and at this time I can set up the Max Units for a
resource on a particular project. (This way Joe works on Proj1 70% and Proj2
30% and I just enter the work time and the duration gets calculated correctly.
I specify the tasks, assign resources, units of work, etc. All fine.
THEN later, I decide that my resources need to be juggled. I want to
experiment or change permanently from now going forward and have Joe on
project 1 50% of the time so I can put him on some other project that extra
20% of the time.
I can change Joe's max units, but it seems to only affect New tasks, not
existing ones. I want my existing schedule (all work not completed) to be
updated by this decrease in Joe's availability
I set up my resources and at this time I can set up the Max Units for a
resource on a particular project. (This way Joe works on Proj1 70% and Proj2
30% and I just enter the work time and the duration gets calculated correctly.
I specify the tasks, assign resources, units of work, etc. All fine.
THEN later, I decide that my resources need to be juggled. I want to
experiment or change permanently from now going forward and have Joe on
project 1 50% of the time so I can put him on some other project that extra
20% of the time.
I can change Joe's max units, but it seems to only affect New tasks, not
existing ones. I want my existing schedule (all work not completed) to be
updated by this decrease in Joe's availability