V
VDU
Hello,
I'm using MS Project 2007 for analysis, not for planning. So I want to ask
how can I automatically calculate resource charge/ task (human resources)
given the fact that in case of multitasking, the resource should be allocated
equally per task (with a percentage)?
Basically, I have a resource that had 2 tasks which at some point overlap
each other. The resource worked on task 1 for 3 days, on both tasks for 2
days (50-50) and on the second for 10 days. Overall, Task 1 required 4 days
and task 2 - 9 days. How can I calculate the same for much more complex
situations? (more resources, much more tasks/resource)
Thank you,
I'm using MS Project 2007 for analysis, not for planning. So I want to ask
how can I automatically calculate resource charge/ task (human resources)
given the fact that in case of multitasking, the resource should be allocated
equally per task (with a percentage)?
Basically, I have a resource that had 2 tasks which at some point overlap
each other. The resource worked on task 1 for 3 days, on both tasks for 2
days (50-50) and on the second for 10 days. Overall, Task 1 required 4 days
and task 2 - 9 days. How can I calculate the same for much more complex
situations? (more resources, much more tasks/resource)
Thank you,